DETOUR: Holly Springs Rd/McIngvale Rd Roundabout Construction

Beginning April 1, 2025

Post Date:03/27/2025 5:00 PM

Hollysprings & Mcingvale Detour Plan

City of Hernando Travel Circle Project (McIngvale Road and Holly Springs Road):
The following notice concerns information for proposed construction for the next 40 days at the intersection beginning April 1, 2025. Contractors will be on site the week of April 1 to prepare the intersection with asphalt paving of the areas that are presently gravel, and other construction items that the area needed. On April 7, the contractor will begin the process of setting up a detour so that the intersection can be closed in order to construct the center section of the Travel Circle and the Traffic Islands. Expect the intersection to be closed for 30 days, depending on the weather. Signs will be installed on McIngvale, Holly Springs, Monteith, Summit, Greenwich and Stonehenge Drive.